Comparative Analysis of Planning with the Critical Path Method, Last Planner System, and Location-Based Techniques in Brazil, Finland, and the United States
No Thumbnail Available
Access rights
openAccess
Journal Title
Journal ISSN
Volume Title
A1 Alkuperäisartikkeli tieteellisessä aikakauslehdessä
This publication is imported from Aalto University research portal.
View publication in the Research portal
View/Open full text file from the Research portal
Other link related to publication
View publication in the Research portal
View/Open full text file from the Research portal
Other link related to publication
Date
2023
Department
Department of Civil Engineering
Major/Subject
Mcode
Degree programme
Language
en
Pages
20
Series
EMJ - Engineering Management Journal
Abstract
The Critical Path Method (CPM), the Last Planner System (LPS) and location-based methods, such as the Line of Balance (LB), are discussed extensively in the technical literature about schedules. However, no discussion exists focusing on the differences and similarities of these methods in terms of their use in different countries. Using chi-squared and Fisher’s exact tests, this research compared three countries (Brazil, Finland, and United States) and the methods to evaluate both intra- and inter-country implementation to gain additional insights about their use. Results suggest statistically significant intra- and inter-country differences regarding how these methods are used, with a specific focus on mechanics in the countries, offering important information to address their various scheduling needs. The results reflect the current state of practice; engineering and construction managers should understand different ways of understanding scheduling. Such understanding can lead to more efficient communication with collaborators and when incorporating foreign teams in projects. The study identifies the need for further scientific explanation as to why these methods are used in the manner they are intra-country as well as adaptions made in inter-country relationships.Description
Publisher Copyright: © 2022 American Society for Engineering Management.
Keywords
Critical Path Method, Last Planner System, location-based scheduling, Program & Project Management, Scheduling
Other note
Citation
Scala, N M, Schiavone, V, Olivieri, H, Seppänen, O, Alves, T D C L, Liu, M & Granja, A D 2023, ' Comparative Analysis of Planning with the Critical Path Method, Last Planner System, and Location-Based Techniques in Brazil, Finland, and the United States ', EMJ: Engineering Management Journal, vol. 35, no. 3, pp. 237-256 . https://doi.org/10.1080/10429247.2022.2069981