Adaptive Robust Short-Term Planning of Electrical Distribution Systems Considering Siting and Sizing of Renewable Energy-based DG Units
Loading...
Access rights
openAccess
acceptedVersion
URL
Journal Title
Journal ISSN
Volume Title
A1 Alkuperäisartikkeli tieteellisessä aikakauslehdessä
This publication is imported from Aalto University research portal.
View publication in the Research portal (opens in new window)
View/Open full text file from the Research portal (opens in new window)
Other link related to publication (opens in new window)
View publication in the Research portal (opens in new window)
View/Open full text file from the Research portal (opens in new window)
Other link related to publication (opens in new window)
Date
2019-01-01
Major/Subject
Mcode
Degree programme
Language
en
Pages
12
Series
IEEE Transactions on Sustainable Energy, Volume 10, issue 1, pp. 158 - 169
Abstract
Short-term planning is a decision-making process that aims at ensuring proper performance of electrical distribution systems (EDSs) within a short period of time. In recent years, this process has faced a significant challenge due to the integration of renewable energy-based technologies. To handle such complicated planning problem most suitably, sophisticated algorithms are required. This paper proposes a mixed-integer linear programming model to find the optimal short-term plan of EDSs considering siting and sizing of capacitor banks and renewable energy sources, conductor replacement of overloaded circuits, and voltage regulators allocation. Besides considering the economic aspects, the environmental issues are also considered to promote a low carbon emission system. To address the uncertainties of electricity consumption and renewable energy output power, a two-stage robust optimization model is used, and to handle this model more efficiently, the column and constraint generation algorithm is applied. A 135-node distribution system is studied under different conditions to assess the performance of the proposed approach. Results show that the planning actions, for each case study, improve the efficiency of EDS and mitigate the pollutant emissions at the distribution level.Description
Keywords
planning, reactive power, robustness, integrated circuit modeling, power generation, adaptation, models, conductors
Other note
Citation
Melgar Dominguez, O D, Pourakbari Kasmaei, M & Mantovani, J R S 2019, ' Adaptive Robust Short-Term Planning of Electrical Distribution Systems Considering Siting and Sizing of Renewable Energy-based DG Units ', IEEE Transactions on Sustainable Energy, vol. 10, no. 1, 8341816, pp. 158 - 169 . https://doi.org/10.1109/TSTE.2018.2828778