Productivity effects of starting as early as possible in hospital construction

Loading...
Thumbnail Image

Access rights

openAccess

URL

Journal Title

Journal ISSN

Volume Title

A4 Artikkeli konferenssijulkaisussa

Date

2013

Major/Subject

Mcode

Degree programme

Language

en

Pages

9
626-635

Series

Proceedings of the 21st Ann. Conf of the Int'l Group for Lean Construction

Abstract

Critical Path Method (CPM) is the standard scheduling methodology for building construction in the US. The objective of this research is to determine the effect of management strategies focusing on early starts (ASAP strategy) on the production and productivity rates of "critical path" tasks in a construction schedule. In this study, two healthcare projects were followed over the course of construction to document the effects of field management decisions on production. On project one, a CPM schedule and ASAP strategy was used exclusively to manage subcontractor resources. On project two, both CPM/ASAP and Location Based Management System (LBMS) strategies were used in parallel, on similar location groups, enabling direct comparison. Actual activity start dates, finish dates, demobilizations and remobilizations, productivity and production rates, and manpower were recorded weekly for analysis. On project one, the actual dates and rates are compared against the CPM plan to determine how reliably the tasks could be completed using the ASAP "work in place" management strategy. Results show that certain deviations from the CPM plan, such as starting early, relocating resources before completing a location, and deploying resources to multiple locations at a time cause unpredictable dates of completion and frequent changes to the "critical path". On project two, actual productivity and production rates for selected tasks are compared between the CPM/ASAP and LBMS location groups. Results show that deploying resources to a location as soon as it is available can have a negative effect on the productivity and overall production rates of critical tasks.

Description

Keywords

Continuous, CPM, flow, LBMS, process, production, variability

Other note

Citation

Evinger, J, Mouflard, C & Seppänen, O 2013, Productivity effects of starting as early as possible in hospital construction . in Proceedings of the 21st Ann. Conf of the Int'l Group for Lean Construction . Fortaleza, Brazil, pp. 626-635 .