Operational release planning in large-scale Scrum with multiple stakeholders - A longitudinal case study at F-Secure Corporation
Loading...
Access rights
openAccess
publishedVersion
URL
Journal Title
Journal ISSN
Volume Title
A1 Alkuperäisartikkeli tieteellisessä aikakauslehdessä
This publication is imported from Aalto University research portal.
View publication in the Research portal (opens in new window)
View/Open full text file from the Research portal (opens in new window)
View publication in the Research portal (opens in new window)
View/Open full text file from the Research portal (opens in new window)
Date
Department
Major/Subject
Mcode
Degree programme
Language
en
Pages
Series
Information and Software Technology, Volume 57, pp. 116-140
Abstract
Context The analysis and selection of requirements are important parts of any release planning process. Previous studies on release planning have focused on plan-driven optimization models. Unfortunately, solving the release planning problem mechanistically is difficult in an agile development context. Objective We describe how a release planning method was employed in two case projects in F-Secure, a large Finnish software company. We identify the benefits which the projects gained from the method, and analyze challenges in the cases and improvements made to the method during the case projects. Method We observed five release planning events and four retrospectives and we conducted surveys in the first two events. We conducted six post-project interviews. We conjoined the observation notes, survey results and interviews and analyzed them qualitatively and quantitatively. Results The focal point of the method was release planning events where the whole project organization gathered to plan the next release. The planning was conducted by the development teams in close collaboration with each other and with the other stakeholders. We identified ten benefits which included improved communication, transparency, dependency management and decision making. We identified nine challenges which included the lacking preparation and prioritization of requirements, unrealistic schedules, insufficient architectural planning and lacking agile mindset. The biggest improvements to the method were the introduction of frequent status checks and a big visible planning status board. Conclusion The release planning method ameliorated many difficult characteristics of the release planning problem but its efficiency was negatively affected by the performing organization that was in transition from a plan-driven to an agile development mindset. Even in this case the benefits clearly outweighed the challenges and the method enabled the early identification of the issues in the project.Description
VK: Lassenius, C.; Project: N4S; Group: SPRG
Other note
Citation
Heikkila, V T, Paasivaara, M, Rautiainen, K, Lassenius, C, Toivola, T & Järvinen, J 2015, 'Operational release planning in large-scale Scrum with multiple stakeholders - A longitudinal case study at F-Secure Corporation', Information and Software Technology, vol. 57, pp. 116-140. https://doi.org/10.1016/j.infsof.2014.09.005