Intelligent Scheduling for Underground Mobile Mining Equipment

Loading...
Thumbnail Image
Journal Title
Journal ISSN
Volume Title
A1 Alkuperäisartikkeli tieteellisessä aikakauslehdessä
Date
2015
Department
Department of Civil and Environmental Engineering
Department of Civil Engineering
Major/Subject
Mcode
Degree programme
Language
en
Pages
1-21
Series
PLoS One, Volume 10, issue 6
Abstract
Many studies have been carried out and many commercial software applications have been developed to improve the performances of surface mining operations, especially for the loader-trucks cycle of surface mining. However, there have been quite few studies aiming to improve the mining process of underground mines. In underground mines, mobile mining equipment is mostly scheduled instinctively, without theoretical support for these decisions. Furthermore, in case of unexpected events, it is hard for miners to rapidly find solutions to reschedule and to adapt the changes. This investigation first introduces the motivation, the technical background, and then the objective of the study. A decision support instrument (i.e. schedule optimizer for mobile mining equipment) is proposed and described to address this issue. The method and related algorithms which are used in this instrument are presented and discussed. The proposed method was tested by using a real case of Kittilä mine located in Finland. The result suggests that the proposed method can considerably improve the working efficiency and reduce the working time of the underground mine.
Description
VK: T20703
Keywords
mining, mobile, optimize, scheduling, underground
Other note
Citation
Song , Z , Schunnesson , H , Rinne , M & Sturgul , J 2015 , ' Intelligent Scheduling for Underground Mobile Mining Equipment ' , PloS one , vol. 10 , no. 6 , e0131003 , pp. 1-21 . https://doi.org/10.1371/journal.pone.0131003