Using an Integrated 5D & location-based planning system in a large hospital construction project
Loading...
Journal Title
Journal ISSN
Volume Title
A1 Alkuperäisartikkeli tieteellisessä aikakauslehdessä
This publication is imported from Aalto University research portal.
View publication in the Research portal
View/Open full text file from the Research portal
Other link related to publication
View publication in the Research portal
View/Open full text file from the Research portal
Other link related to publication
Date
2010
Major/Subject
Mcode
Degree programme
Language
en
Pages
102-112
Series
LEAN CONSTRUCTION JOURNAL
Abstract
Hypotheses: H1: model-based constructability based on a parallel construction model should identify more constructability issues than traditional model-based constructability processes. H2: model-based quantity takeoff should take less time than manual take-off. H3: integrated location-based scheduling should enable schedule optimization over CPM–based approaches, resulting in shorter overall duration with more continuous resource use. Purpose: The goal of this paper is to present the case study of Kaiser Oakland hospital project, the largest known implementation of integrated 5D systems combined with location-based planning. Research Design/Method: Parallel processes were implemented in the project. The results of integrated 5D system were compared to the results of traditional constructability, estimating and scheduling processes. Findings: H1 and H3 were supported in the preconstruction of foundations. Over 200 additional constructability issues were identified using the construction model. Location-based scheduling enabled the planning of continuous work for subcontractors while compressing the duration of Foundation phase by six weeks. Contrary to the hypothesis H2 there was no time saving benefits related to quantity take-off, although there were some qualitative benefits in terms of better communication. Limitations: Only Foundation phase was analyzed. Parallel processes are a form of waste. Implications: Integrated 5D system was shown to provide better results for constructability and scheduling. Value for practitioners: Practitioners can learn from the challenges discussed in the paper. Use of an integrated 5D system has not been described in technical literature before using a case study of this size.Description
Keywords
location-based management, constructability, 5D model, flowline schedule
Other note
Citation
Kala , T , Seppänen , O & Stein , C 2010 , ' Using an Integrated 5D & location-based planning system in a large hospital construction project ' , LEAN CONSTRUCTION JOURNAL , pp. 102-112 . < http://www.leanconstruction.org/media/docs/lcj/2010/LCJ_10_018.pdf >