Title: | Managing the delivery and commissioning of nearly zero-energy building projects Tuotannon hallinta ja toiminnan varmistaminen lähes nollaenergiarakennusprojekteissa |
Author(s): | Kantola, Mikko |
Date: | 2015 |
Language: | en |
Pages: | 96 + app. 86 |
Department: | Rakennustekniikan laitos Department of Civil and Structural Engineering |
ISBN: | 978-952-60-6339-3 (electronic) 978-952-60-6338-6 (printed) |
Series: | Aalto University publication series DOCTORAL DISSERTATIONS, 117/2015 |
ISSN: | 1799-4942 (electronic) 1799-4934 (printed) 1799-4934 (ISSN-L) |
Supervising professor(s): | Puttonen, Jari, Prof., Aalto University, Department of Civil and Structural Engineering, Finland |
Thesis advisor(s): | Saari, Arto, Prof., Tampere University of Technology, Finland |
Subject: | Civil engineering, Economics, Energy |
Keywords: | nearly zero-energy building, commissioning, project delivery system, IPD, renewable energy, lähes nollaenergiatalo, toiminnan varmistaminen, hankemuoto, allianssi, uusiutuva energia |
Archive | yes |
OEVS yes | |
|
|
Abstract:EU on asettanut tulevaisuuteen kunnianhimoiset päästövähennystavoitteet. Osana tavoitteita on luotu EPBD ja RES direktiivit, joiden mukaan kaikkien uusien rakennusten tulee olla lähes nollaenergiarakennuksia (nZEB) vuoden 2020 jälkeen. Korkea energiatehokkuus ja tontilla tuotettu uusiutuva energia ovat nZEB määritelmän ydin asiat. Tekniset ratkaisut, joilla nuo tavoitteet saavutetaan pohjoisessa ilmastossa, ovat: tehokas eristys, ilmatiivis vaippa, moderni talotekniikka ja uusiutuvat energiahuoltoratkaisut, kuten PV-paneelit ja maalämpö. |
|
Parts:[Publication 1]: Kantola M and Saari A (in press), Identifying and managing risks involved in the transition to the EU nZEB decree, Facilities.[Publication 2]: Kantola M and Saari A (2013), Renewable vs. traditional energy management solutions – a Finnish hospital facility case, Renewable Energy, Vol. 57 pp. 539-545. DOI: 10.1016/j.renene.2013.02.023 View at Publisher [Publication 3]: Kantola M and Saari A (2014), Ensuring the functionality of a nearly zeroenergy building with procurement methods, Facilities, Vol. 32 No. 7 pp. 312-323. DOI: 10.1108/F-05-2012-0040 View at Publisher [Publication 4]: Kantola M and Saari A (in press), Project delivery systems for nZEB projects, Facilities.[Publication 5]: Kantola M and Saari A (2014), Commissioning for nearly zero-energy building projects, Construction Innovation: Information, Process, Management, Vol. 14 No. 3 pp. 370-382. |
|
|